Silver Eagle ManufacturingCall
Manuals / TP-60-3 Parts and Svc Manual _rev11-21-06_.pdf

TP603

TP-60-3 Parts and Svc Manual _rev11-21-06_.pdf

Rev
rev 11-20-06
Pages
44
Parts
0

Service Procedures

1. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Mount new cables with anchor and cotterpins on bottom panel and bring cable stop end to top of door

1. Installation, repairs andadjustments must be made by · INSTALLATION

CABLE REPLACEMENT PROCEDURE (WITH TENSION ON SPRING)

1. Brake adjustment · ADJUSTMENT

Securely clamp the track below the panel to be replaced to prevent the door from rising.

1. Installation, repairs andadjustments must be made by · INSTALLATION

Close door from inside. Release spring tension from cables by fully inserting 1/2" diameter x 18" winding

1. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Spring anchor plug and right-hand cable drum mount on curbside, 6-hole spring winding plug and left-

1. Brake adjustment · ADJUSTMENT

- Torque wheel nut

1. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Close door from inside. Clamp counterbalance shaft with vise grip handle against ceiling to keep cables

2. Installation, repairs andadjustments must be made by · INSTALLATION

Raise bar enough to allow inserting of second winding bar into lower hole and release tension to let

2. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Cables come off front side of cable drums, between door face and header.

2. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Insert the cable stop end into the cable drum slot. Thread the cable into the groove nearest the slot and

2. Brake adjustment · ADJUSTMENT

Drill out rivets on hinge halves of the panel to be replaced and pry the hinge half loose.

2. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Release spring tension from shaft by fully inserting 1/2" diameter x 18" winding bar into one of the spring

3. Brake adjustment · ADJUSTMENT

Lift the door panels above the panel to be replaced into the horizontal track and secure with vise grips

3. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Maintaining tension on the cable, slide the cable drum on the counterbalance shaft against the bearing

3. Installation, repairs andadjustments must be made by · INSTALLATION

Loosen set screws on cable drums, releasing cable drum from shaft, remove cable(s) from cable drum(s).

3. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

After loosening spring winding plug set screws, use both winding bars to add (lift up) or remove (lower

3. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Vise grip clamps against lower header flange to keep cables tight while winding spring.

4. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

After adjusting the spring tension, properly tighten set screws onthe spring winding plug and remove vise

4. Brake adjustment · ADJUSTMENT

Remove the old panel, line up the new one and drill all of the hinge holes on the bottomof the new panel.

4. Installation, repairs andadjustments must be made by · INSTALLATION

Removecable(s) from door bottom panel by removing anchor and

4. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Clamp counterbalance shaft with vise grip handle against ceiling to keep cables tight. (Fig. 3)

4. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Counterbalance spring winds downward.

5. Installation, repairs andadjustments must be made by · INSTALLATION

Remove cable(s) from door bottom panel by removing anchor and CAUTION:Raising

5. Brake adjustment · ADJUSTMENT

Insert bolts in the holes, install the hinges over the bolts and tighten the nuts.

5. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Repeat cable mounting procedure for opposite side, making sure drums are against bearings, set screws

5. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Cable anchors are mounted at 4-1/8" from panel edge to centerline.

6. Brake adjustment · ADJUSTMENT

Lower the door from the horizontals and drill all the holes in top of the panel.

6. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Counterbalance shaft length isopening width minus 1-1/8".

6. Brake adjustment · ADJUSTMENT

000 miles or Consult axle maintenance for the following:

6. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Determine the number of winds needed for the counterbalance spring by dividing the door opening height

6. Installation, repairs andadjustments must be made by · INSTALLATION

Mount new cables with anchor and cotter pins on bottom panel and or damage to

7. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Run a chalk mark the full length of the counterbalance spring (Fig. 1). Leavevise grips clamped to the

7. Installation, repairs andadjustments must be made by · INSTALLATION

Insert the cable stop end into the cable drum slot. Thread the cable 5 must be done by

7. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Treat the electrical system as you would the chassis. Lubricate sockets, pigtails, battery

7. Brake adjustment · ADJUSTMENT

Check electrical harness

7. Brake adjustment · ADJUSTMENT

With the upper door section clamped so it will not fall, tip the paneltoward you to insert the bolts. Install

8. Installation, repairs andadjustments must be made by · INSTALLATION

Maintaining tension on the cable, slide the cable drum on the winding bar in place.

8. Brake adjustment · ADJUSTMENT

The replacement of the panel is now complete.

8. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Fully insert 1/2" diameter by 18" winding bar into one of the spring winding plug holes. Loosen set screws

8. Brake adjustment · ADJUSTMENT

Check all fasteners

8. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Inspect for improper ground connections. This is a major cause of lamp failure, especially

9. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Always replace wiring, trailer light cables, and harnesses with an equal or heavier

9. Installation, repairs andadjustments must be made by · INSTALLATION

Repeat cable mounting procedure for opposite side, making suredrums are against bearings,

9. Brake adjustment · ADJUSTMENT

Check rear bumper and fasteners

10. Installation, repairs andadjustments must be made by · INSTALLATION

Release spring tension by rotating spring windingplug just far enough to allow removal of winding bar

10. Brake adjustment · ADJUSTMENT

Check Kemlite roof for damage

10. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Inspect the grommets that house the lamps. As they age, they eventually will deteriorate

11. Brake adjustment · ADJUSTMENT

Lubricate the counterbalance, bearings, rollers, hinges and lock liberally with TODCO Lube. Do not use grease.

11. SPRING RE-ADJUSTMENT PROCEDURE (WITH CABLES MOUNTED) · ADJUSTMENT

Apply the cleaner, working it across the surface in a scrubbing or circular motion. Rinse thoroughly to remove all

12. Brake adjustment · ADJUSTMENT

Lube or any petroleum-based lubricant on rubber door seals. Please refer to serial number for replacement parts.

13. Brake adjustment · ADJUSTMENT

INTERMEDIATE AND TOP PANEL REPLACEMENT

TP-60-3 Parts and Svc Manual _rev11-21-06_.pdf | Silver Eagle Manufacturing